Palmetto Parkway - Finishing the job in Aiken County

Calendar

Construction Start Date - 1/2/07

Detours
Detours
Old Bradleyville Road
Ascauga Lake Road
Whitehall Road
Begin Detour
3/07
12/07
5/08
End Detour
11/07 complete
10/08 complete
6/08 complete
New Roadway Alignments
New Roadway Alignments
Radio Station Road
McKinney Lane
Carolina Springs Spur
US-25 (over I-20) - stage 1
US-25 (over I-20) - stage 2
US-25 Connector
Old Bradleyville Road
Powerhouse Road
Clearwater Road
Laurel Lakes Drive
Begin Work
2/07
2/07
3/07
3/08
2/09
3/07
5/07
5/07
5/07
7/07
Shift Traffic
6/07 complete
9/07 complete
12/07 complete
2/09 complete
11/09 complete
4/09 complete
12/07 complete
3/08 complete
7/08 complete
8/08 complete
Bridgework
Bridgework
Old Bradleyville Road
Powerhouse Road over I-520
I-520 over US-25 Connector
I-520 over Old Aiken Road
I-520 Ramp B over I-520 Flyover
I-520 Flyover over I-20
I-520 Ramp D over I-20 Ramp A
I-520 over Clearwater Road (SC-126)
I-520 over Atomic Road (SC-125)
Ascauga Lake Road over I-520
I-520 Ramp B over I-20
US-25 over I-20 - stage 1
US-25 over I-20 - stage 2
Drive Pile
5/07
5/07
6/07
6/07
8/07
10/07
11/07
10/07
12/07
2/08
10/07
5/08
3/09
Deck Complete
11/07 complete
12/07 complete
2/08 complete
3/08 complete
3/08 complete
3/09 complete
9/08 complete
6/08 complete
10/08 complete
9/08 complete
1/09 complete
10/08 complete
9/09 complete
** I-520 Phase 2 opened to Traffic on 12/17/09 **
** Contract Completion Date - December 31, 2009 **